As part of the 2017/18 Timber Bridge Inspections program, a bridge on Hartley Vale Road, just outside the township of Hartley Vale has been identified as requiring urgent reconstruction to its failed sandstone abutments.

The cause of the sudden and significant damage to the existing sandstone abutments of the bridge is currently unknown and as such, inspections are being carried out twice per day by both Council engineers and local bridge construction experts. A 5 tonne load limit has been placed on the bridge to minimise further damage and community impact by restricting heavy vehicle traffic while still allowing residential and light vehicle through traffic.

Works are already underway on the procurement of a temporary single span bridge to be constructed immediately adjacent to the existing bridge to divert traffic and minimise disruption to local residents while the cause of damage and methods of remediation are investigated. This temporary bridge will have a load capacity of 25 tonnes and will serve to provide temporary access to all but the largest of heavy vehicles. It is expected that this bridge will be in place mid next week.

Both Council engineers and local bridge experts will be working towards a solution to this issue as a priority through thorough structural and geotechnical investigation and design. Lithgow City Council appreciates the patience of the community during the construction of the temporary bridge and apologises in advance for any inconvenience that these necessary and urgent works may cause.

 
Yarrabin Guest Property Yarrabin Guest Property Yarrabin Guest Property Ride ~ Relax ~ Reconnect

Recent News

Solar Panel and Battery Installation – Lithgow Council Administration Building
Solar Panel and Battery Installation – Lithgow Council Administration Building
To reduce energy costs and provide a power contingency measure, Counci...
HIP National Orchestra Announces Largest Ever Season
HIP National Orchestra Announces Largest Ever Season
ILLUMINATE THE PAST | EVOKE THE PRESENT | EMERGE INTO THE FUTURE
<br...
Gavin Bowles releases debut album 'This Year's Modern'
Gavin Bowles releases debut album 'This Year's Modern'
Following on from the single releases of The Daily Grind and Apartmentality,...
Temporary Closure: Section of Prince Henry Cliff Walk, Leura
Temporary Closure: Section of Prince Henry Cliff Walk, Leura
National Parks & Wildlife Service
Blue Mountains National Park –...

What's New

Jenolan Caves have reopened some caves
Jenolan Caves have reopened some caves
Jenolan Caves Exclusive weekend accommodation or Chisolm's dining cave experiences available now.
The ATO's cyber security checklist +++
The ATO's cyber security checklist +++
Trumans Chartered Accountants Trumans November Newsletter now available. What does the “full expensing” write-off deduction mean for business?
COVID Safe Wedding Celebrant
COVID Safe Wedding Celebrant
Marriage Celebrant - A Ceremony by Design A Ceremony by Design is seizing the opportunity to re-imagine weddings for the 2020s.
The perfect place to relax this summer
The perfect place to relax this summer
Melaleuca Mountain Retreat Views that will leave you breathless, a place to relax. Melaleuca Mountain Retreat offers the perfect getaway !!
Limited Weekend Escapes Remaining
Limited Weekend Escapes Remaining
Seclusions Looking for a weekend escape to relax & unwind?
Also in this Section

Have You Visited

Announcement
Jenolan Caves have reopened some cavesExclusive weekend accommodation or Chisolm's dining cave experiences available now.View Jenolan Caves »